Groundwater – Upcoming Activities

Late Summer/Fall 2018

  • Continue TGTS operations.
  • Perform compliance monitoring sampling campaigns in accordance with the 100% Temporary Treatment Design Report.
  • Continue design and begin procurement process of the final treatment system.
  • Complete design of the Treatment Building and permit equivalency process with the Town of Acton.

Last updated on July 31, 2018