• slideshow_large
  • slideshow_large
  • slideshow_large

Latest NMI News Recent Documents

Building Demolition Nearing Completion

Building E Mezzanine Demolition

Building E Mezzanine Demolition

Demolition of Building A, the final building structure to be demolished, began last week and is approximately 50% complete. Building E demolition is complete and placement of liner over the slab is nearly complete. For a summer demolition update, see Demo Progress 24JUN – 7 JUL 2016.

Buildings Demolished

Buildings B, B4, C and D have been completely demolished. The liner has been placed over the former Building D location and demolition continues towards the south end of Building C. The demolition crews have removed about half of Building E and are continuing demolition this week. Building A will be the final building removed. For more photos on demolition, see NTCRA Progress.

3JUN16 Aerial

Building Demolition Continues

Building demolition continues onsite with Building D demo nearly complete. The crew will be approaching Building C demo this week and the liner/cover crew will be mobilizing next week. April progress can be viewed on this slideshow.

Community Involvement  Recent Documents

EPA Issues Fact Sheet on NMI Activities Update

In light of building demolition resuming on 19APR16, EPA issued a fact sheet to update on the status of activities on site and the various winter activities performed for the test of the Assabet 1A and 2A production wells to define the “capture zone,” which will assist in determining an effective location to install and test a pumping well.

CREW and 2229 Main Street met with Agencies on site on 17 March 2015

Public groups and de maximis met with the Agencies on 17 MAR 2015 on site to discuss the NTCRA status and schedule for building demolition as well as the planning for the remedy for 1, 4-dioxane in groundwater. The 2229 Main Street Committee provided an update to the Town’s approach to potentially taking the Site.

Last updated on July 19, 2016