*Please note that these dates are approximate and represent our best estimates.
Spring 2013:
- Complete and submit Pre-Demolition Survey Report.
- Continue site security and control activities.
- Continue building stabilization activities.
- Implement Phase 1 Construction Activities.
- Perform limited site improvements identified in the Site Management and Security Plan Addendum #1.
- Execute contracts for transportation & disposal and high hazard work.
Summer / Fall 2013:
- Proceed with removal of equipment
Winter / Spring 2014:
- Prepare third set of Construction Submittals, addressing demolition of buildings and installation of temporary cap over foundation slabs
Summer / Fall 2014:
- Proceed with demolition and capping