RI/FS Upcoming Activities

*Please note, some dates or time frames are approximate and represent our best estimates.

Winter 2016

  • Continue installation of groundwater wells for investigation related to 1,4-dioxane.
  • Complete field activities associated with the Groundwater Investigation Work Plan, including hydraulic testing and another round of collecting groundwater elevations.
  • Perform data analysis and preparation of the investigation report.

 Spring 2016

  • Continue data analysis of the Groundwater Investigation and preparation of the report.

Last updated on February 1, 2016